Woods Creek Reach 10 RestorationThe intent of the Woods Creek Reach 10 Restoration project is to stabilize approximately 1,817 linear feet of Woods Creek and improve the adjacent wetlands back to their native conditions. The general scope of work required will consist of:

  • The removal of non-native vegetation
  • Streambank restoration
  • Tree removal
  • Seeding of native vegetation
  • Installation of toe slope protection
  • Stream bank grading along Woods Creek

Woods Creek Streambank Restoration ProjectTwo open house meetings were held (August 22nd and August 27th) to discuss the project in more detail. The presentation materials from the open houses are available for viewing at the bottom of this page and provide additional information on the project.

Updates

January 15, 2020: The Village hired contractor completed most of the project in 2019 and the contractor will return this spring to complete the project.

Public Right-of-Way

Please note that all work will be performed within the Village right-of-way. If you have any type of existing features within the Village right-of-way area (i.e. sprinkler system, landscape features, fire pits, electronic “invisible” dog fence, etc.), precautions should be taken by you, the property owner, to remove these items to prevent damage to them during construction. The Village will not repair or replace private property left within the Village right-of-way.

Contact

The contract for this work has been awarded to Applied Ecological Services, Inc. of Huntley, IL as the general contractor for this project.

Guy Fehrman, LITH Superintendent of Streets, will be the Village representative for the project. Guy may be reached at 847-960-7507 or lfehrman@lith.org.

Chad Pieper, LITH Village Engineer, will be the project manager for the project. Chad may be reached at 815-759-8346 or cpieper@hrgreen.com.

Joshua Schmitt, Construction Technician III, will be the on-site engineer performing construction inspections and acting as the field liaison to residents and property owners. Josh may be reached at 815-276-2081 or jschmitt@hrgreen.com.