05-31-2024
This past week community members were able to see crews begin to set up the construction site fencing around the property, continue working on site grading, working on adding site utilities, excavating and preparing for concrete to start in the next several weeks.
Click HERE for today's updated photos.
05-24-2024
This past week community members watched as crews continued excavation and land clearing, began adding site utilities and started ground leveling.
Next week, community members can expect a continuation of the same; land clearing, moving dirt from the build site, utilities, digging, leveling and site preparation.
Click HERE for today's updated photos.
05-17-2024
This past week the crew continued excavation and land clearing and started preparation for site utilities.
Next week, community members can expect more of the same; land clearing, moving dirt from the build site and adding site utilities.
Click HERE for today's updated photos.
05-10-2024
This past week the crew continued more excavation and land clearing. It is already starting to take on some shape.
Next week, community members can expect more of the same; land clearing and moving dirt from the build site and preparation for site utilities.
Click HERE for today's updated photos.
05-03-2024
This past week the crew continued excavation and land clearing. Due care was taken to preserve the existing bricks as they were moved by the team to ensure they will be transferred safely to the new location of the Veterans Memorial upon conclusion of the construction. The memorial will be refreshed and relocated on the property, closer to the roadway, which should provide additional visibility for passers-by.
After the relocation, the Veterans Memorial will remain accessible as a commemorative gathering space to honor those who served.
Next week, community members can expect more of the same; land clearing and moving dirt from the build site.
Click HERE for today's updated photos.